CONTRACT TITLE

DESCRIPTION OF WORKS

DETAILS OF WORK CONTENT

CONTRACT PERIOD

COUNTRY WHERE WORK PERFORMED

CONTACT DETAILS

Aflease Uranium Contract

SMP Contract for Uranium One

1100 Tonnes Steelwork
400 Pieces Mechanical Equipment
Fabrication & Installation of CarbonSteel, Stainless, Duplex, SuperDuplex and Titanium Piping.

Start: March 2006

End: October 2007

South Africa

Klerksdorp

Mr D. Jooste

Bateman Engineering Projects

Pande Flow lineInstallation

Install Piping Above and Below Ground

Installation of 43km's of piping

Start: January 2007

End: December 2008

Mozambique

Temane

Mr P. Brown

WK Construction

Transnet Reefer Structures

Supply, Fabrication and Erection of 60 off Reefer Structures

580 Tonnes Steelwork

Start: February 2008

End: October 2008

South Africa

Port Elizabeth

Mr G. Clark

HMG J/V

SAPREF 2009 Turnaround

Repairs and replacement of piping & Equipment

Refinery Shutdown - Workforce peak @ 630 DFL & IFL

Start: Oct 2008

End: Sept 2009

South Africa

Durban

Mr C. Mensing

SAPREF

Ambatovy Nickel Project

Piping Fabrication for the Ambatovy Nickel Project

30,000 Weld inches

Start: Sept 2008

End: June 2009

South Africa

Durban

Mr M. Hughes

Bateman Projects Limited

Waltloo Upgrade Project

Mechanical Upgrade of theWaltloo Depot of TransnetPipelines

Installation of mechanicalequipmentand piping

Start: August 2009

End: October 2011

South Africa

Waltloo, Pretoria

Mr R. Poninjhaus

Siemens

Langlaagte Upgrade Project

Mechanical Upgrade of theLanglaagte Depot ofTransnet Pipelines

Installation of mechanical equipmentand piping

Start: August 2009

End: October 2011

South Africa

Langlaagte, JHB

Mr R. Poninjhaus

Siemens

 

2011 Turnaround

Repairs and replacement of piping & Equipment

Refinery Shutdown - Workforce peak @ 700 DFL

Start: Feb 2011

End: October 2011

South Africa

Durban

Mr C. Mensing

SAPREF

Oleum Boiler

Supply, Fabrication and Installation

Manufacture of 1 x Oleum Boiler

Start: Aug 2011

End: Dec 2011

South Africa

Durban

Mr R. Tomsett

Chemical initiatives

Provision of Pipeline

SPI-EP-002-8381

Piping Supply, Manufacture,

Delivery and Installation of NewBoiler

Piping: 5.7km's underground (4"line)

Above ground flow line @ manifold

compound

Start: Oct 2011

End: March 2012

Mozambique

Temane

Mr K. Gibbs

Stefanutti Stocks

Hope Bay Gold Project

M7389-P-X-047

Piping Supply, Manufacture,

Delivery and Installation

Piping: 47,000 weld inches

Start: Oct 2011

End: March 2012

South Africa

Durban

Mr S. Brebnor

Bateman Engineering Projects

Sasol - Catalyst Plant Piping

26161-2599C

Piping  Manufacture, Delivery and Installation

Piping: 5,000 weld inches

Start: March 2012

End: June 2012

South Africa

Sasolburg

Mr F. Botha

Foster Wheeler

BP Project Triumph - Phase 1

Nacala

Mechanical and Piping Upgrade

  • Depot

Civil,E & I,Tank repairs and 12" pipe-line replacement

Start: May 2012

End: September 2012

Mozambique

Nacala

Mr S. van Zelst

Triumph Project Manager (BP)

SAPREF Multi-Projects

Multiple SAPREF Contracts

Various Mechanical, Structural &

Piping Contracts

Start: January 2009

End: January 2013

South Africa

Durban

Fluor Igoda

Mr A. Golbaram

BP High Priority Works

- Phase 1

Tank lining, Demolition of 2 x Tanks,Rerouting andreplacement of piping.

Tank re-lining, Demolition of 2 x Tanks, re-routing and replacement of ventpiping.

Start: October 2012

End: December 2012

Mozambique

Beira

Mr T.Mashila

Project Manager (BP)